Mali secures 166 million euro funding for Bamako north 225 kv power loop

Mali has finalized the financing for the Bamako North 225 kV high-voltage power loop project, a strategic initiative to reinforce the capital’s electricity backbone. With a total investment of €166 million, this infrastructure aims to provide reliable and expanded power access to Bamako and its surrounding peri-urban areas. Officials highlight that the project will connect an additional 10,000 households and small businesses while significantly enhancing the power supply quality for nearly 40 industrial facilities.

What does the Bamako North 225 kV loop entail?

The project involves constructing a 103-kilometer double-circuit 225 kV transmission line, linking key locations such as Kodialani, Kambila, Safo, and Dialakorobougou. In addition, two existing substations will be upgraded, and three new ones will be built—two in Safo and one in Kénié—to optimize electricity distribution across the network.

Funding milestones and financial commitments

Approval of the project’s operational phase was granted by Mali’s National Transitional Council in early July, following the ratification of loan agreements signed in February 2026 between the Malian government and a major African development institution. This decision follows earlier financing confirmations, including a €68 million commitment from an Islamic development bank in December 2025, a €43.7 million pledge from a West African development bank in May 2025, and an initial €45 million loan from a European investment institution back in December 2020.

The African Development Bank’s (AfDB) contribution includes multiple financial instruments: a €30.8 million concessional loan through the African Development Fund, a €16.6 million loan via the Transition Support Facility, a €4.4 million climate investment loan, a €5.9 million climate fund grant, and an additional €1.9 million green climate fund grant. Collectively, these funds account for 36.13% of the total project cost, with the Malian government contributing an extra 3.6% in co-financing.

Long-term benefits for Mali’s energy infrastructure

Once operational, the loop will play a critical role in integrating future energy sources into Mali’s grid. It will facilitate the integration of the Guinea-Mali interconnection, the upgraded Manantali 2 transmission line, and upcoming solar power plants in Kambila and Safo—enhancing grid stability and sustainability across the region.